General Information

  • Location: San Antonio, Texas | SW Military & IH-35
  • Owner(s): City of San Antonio Public Works/CPS/Bexar Met/SAWS
  • Engineer: HNTB
  • Contract Amount: $11 million
  • Start Date: December 2010
  • Finish Date: December 2012
  • General Description: Infrastructure improvements consisting of channel excavation, bridges, water lines, sanitary sewer, and natural gas facilities within a two mile vicinity. Part of a multi-phased improvement project.

Key Points

  • 5 separate bridge projects
  • 43000 square yards of concrete paving,
  • 10,000 linear feet of water and wastewater
  • 36” wastewater siphon project,
  • 2000 linear feet of natural gas
  • 50,000 cubic yards of channel excavation
  • 3000 linear feet of large dimension box culverts.